Case Study – Boston Scientific
Boston Scientific
The first step of this project was to upgrade the boiler on site. This generated savings of over 490,000 kWh per year. After the upgrade of the boiler, the cooling system on site also required upgrades.
After the completion of these upgrades, the HVAC system was refurbished. This project allowed savings of 218,641 kWh per year.
The Solution
The on site management then continued by upgrading the lighting on site from halogen and fluorescent lighting to LED fittings. The savings found as a result of this project were 64,744 kWh.
The pumps on site were also improved before a BMS system was installed on site to allow for the accurate monitoring and regulation of the building’s electrical power usage.
Services Provided
Each project is unique and requires a tailored approach. Here are some of the services we provided on this project.
Key Achievements
kWh Annual Energy Savings
Energy Savings Achieved
The energy savings of 969 thousand kWh were achieved through a number of smaller projects such as a boiler upgrade and HVAC upgrades.
Annual Cost Savings
Additional Benefits
The BMS provides useful information on the building and allows for the company to make better decisions about their energy usage.
Annual Co2 Savings
Successful Upgrades
A number of successful upgrades were installed including upgrades to the boiler, cooling, HVAC, lighting, pumps and BMS.